Kansai Electric Power -power with heart-

Nuclear Power Information
Information on Units 3 and 4 of Ohi Power Station (List of Topics)

2018/6/5
Return to Commercial Operation of Ohi Unit No. 4
2018/6/5
Announcement of Return to Commercial Operation of Ohi Unit No.4
2018/5/14
Start of Constant Rated Thermal Power Operation at Ohi Unit No. 4
2018/5/14
Announcement of Start of Constant Rated Thermal Power Operation at Ohi Unit No.4
2018/5/11
Start of Power Generation at Ohi Unit No. 4
2018/5/11
Announcement of Start of Power Control Operation at Ohi Unit No.4 (Connection of Generator in Parallel)
2018/5/10
Announcement of Ohi Unit No.4 Criticality
2018/5/9
Startup of Ohi Unit No. 4
2018/5/9
Announcement of Ohi Unit No.4 Startup
2018/5/8
Schedule of Ohi Unit No. 4 Reactor Startup and Power Control Operation
2018/4/11
Completion of Fuel Loading at Ohi Unit No.4
2018/4/10
Return to Commercial Operation of Ohi Unit No. 3
2018/4/10
Announcement of Return to Commercial Operation of Ohi Unit No.3
2018/4/8
Start of Fuel Loading at Ohi Unit No.4
2018/4/7
Schedule of Start of Fuel Loading at Ohi Unit No.4
2018/3/19
Start of Constant Rated Thermal Power Operation at Ohi Unit No. 3
2018/3/19
Announcement of Start of Constant Rated Thermal Power Operation at Ohi Unit No.3
2018/3/16
Start of Power Generation at Ohi Unit No. 3
2018/3/16
Announcement of Start of Power Control Operation at Ohi Unit No.3 (Connection of Generator in Parallel)
2018/3/15
Announcement of Ohi Unit No.3 Criticality
2018/3/14
Startup of Ohi Unit No. 3
2018/3/14
Announcement of Ohi Unit No.3 Startup
2018/3/13
Schedule of Ohi Unit No. 3 Reactor Startup and Power Control Operation
2018/2/13
Completion of Fuel Loading at Ohi Unit No.3
2018/2/9
Start of Fuel Loading at Ohi Unit No.3
2018/2/8
Schedule of Start of Fuel Loading at Ohi Unit No.3